SEM Building Timeline

Program Validation: June-October 2016
Schematic Design: November 2016-March 2017
Design Development: March- September 2017
Construction Documentation: October 2017 – March 2018
Groundbreaking: December 2018
Construction Completion: December 2020
Furniture, Fixtures, Equipment: January 2021 – May 2021
Opening: Fall Semester 2021 (August)

Veterans Resource Center and Student Activities Center Timeline

Program Validation: December 2016-February 2017
Schematic Design: February-April 2017
Design Development: April- August 2017
Construction Documentation: September 2017 – March 2018
Groundbreaking: December 2018
Construction Completion: February 2020
Furniture, Fixtures, Equipment: March 2020 – May 2020
Opening: Fall Semester 2020 (August)

Veterans Memorial Plaza Timeline

TBA